House Demolition Timeline & Process

From first call to final grade. Typical CNY teardown runs 2 to 3 weeks of active work, with 4 to 6 weeks of permit lead time.

5.0 Stars
117 Reviews Total
OSHA 30
Construction Safety
NYS DOL
Asbestos Licensed
NYS DOL
Public Work Registered
SAM Registered
Federal Contractor
NYSDEC SWPPP
GP-0-20-001 Compliant

The full timeline at a glance

PhaseDurationWhat's happening
1. Site walk + estimate2 to 5 daysWe see the site, write a fixed-price scope
2. Asbestos survey + lab1 to 2 weeksNYS-licensed inspector, bulk samples, written report
3. Permit + utility coordination3 to 5 weeksTown demo permit, National Grid gas, electric, water, sewer
4. Asbestos abatement2 to 5 daysIf ACM is present, removed under containment
5. Structural demolition1 to 2 daysExcavator brings the house down
6. Foundation removal + backfill2 to 4 daysBasement walls, slab, fill, compact
7. Final grade + site cleanup1 dayRough grade, sweep, walk-off

Net: from signed contract to clean lot is typically 6 to 9 weeks. Active equipment time on your property is 5 to 10 working days.

Day by day, once we mobilize

Day 1: Setup

Days 2 to 4: Asbestos abatement (if applicable)

Days 5 to 6: Structural teardown

Days 7 to 10: Foundation, basement, backfill

Day 11: Final grade and walk-off

What we do that most demo contractors don't

Weather and seasonality

We work year-round. CNY winter slows abatement (containment needs heat) and grade work (frozen ground), but structural teardown is fine in any weather. October through April we recommend pushing the final grade to spring.